Blackberry Park Play Area Improvements AB 8523

2 stops across 2 bodies · Aug 5, 2021 → Sep 5, 2023

Summary

AB 8523 authorizes Blackberry Park Play Area Improvements, a capital project spanning from August 2021 through September 2023. Multiple reviews tracked design and construction progress.

Timeline

Each card is one meeting where this item was discussed, oldest first.

Aug 5, 2021 Cemetery Board
Open meeting →
Sep 5, 2023 City Council Regular Meeting Final action here
Action: Accept Project
Carried 6-0
On March 21, 2022 the City Council awarded the contract for the Blackberry Park Play Area Improvements Project, to NW Playground in the amount of $472,140.80 (including sales tax). The completed contract cost was $485,820.73. Two Change Orders totaling $13,679.93 were approved. The first Change Order was for additional leveling and repair of the turf area. The second Change Order was for the repla