← Back to archive  ·  All threads

Policy lifecycle

Holiday Inn Lift Station, Change Order 3 AB 8233

2 stops across 1 body · May 18, 2020 → Sep 7, 2021

Summary

AB 8233 authorizes Change Order 3 for the Holiday Inn Lift Station project. Originally awarded in 2019, the item returned to Council in September 2021 for the construction adjustment.

Timeline

Each card is one meeting where this item was discussed, oldest first.

May 18, 2020 City Council Regular Meeting
Open meeting →
Sep 7, 2021 City Council Regular Meeting Final action here
Action: Authorize
Carried 6-0
On April 15, 2019, the Council awarded the construction contract for the Holiday Inn Lift Station Revisions Project (SEWR 15001) to Road Construction Northwest in the amount of $768,531.50 (including sales tax).
Open meeting →