Confluence Park Pedestrian Bridge Project (Phase II) Construction AB 7194

2 stops across 1 body · Jul 18, 2016 → Aug 1, 2016

Timeline

Each card is one meeting where this item was discussed, oldest first.

Jul 18, 2016 City Council Regular Meeting Final action here
Action: Refer to Council Infrastructure Committee
Carried 6-0
The Confluence Park Phase II construction project provides for: • a publicly-selected, prefabricated timber arch pedestrian bridge (12 feet wide x 135 feet long) with integrated artwork over the main stem of Issaquah Creek • a publicly-selected playground upgrade • a parking lot at Margaret's Meadow • two creek overlook areas (including one at the confluence of the east fork and main stem of Issaq
Open meeting →
Aug 1, 2016 City Council Regular Meeting Final action here
Action: Award Bid; Authorize Additional Funds
Carried 5-2
The Confluence Park Phase II construction project provides for: • a publicly-selected, prefabricated timber arch pedestrian bridge (12 feet wide x 135 feet long) with integrated artwork over the main stem of Issaquah Creek • a publicly-selected playground upgrade • a parking lot at Margaret's Meadow • two creek overlook areas (including one at the confluence of the east fork and main stem of Issaq