Newport Way Landslide Stabilization Project (TR 060) AB 8980

2 stops across 1 body · Sep 16, 2024 → Feb 24, 2025

Summary

Design and construction of stabilization for a landslide on Newport Way that mobilized in a 2020 rainfall event and repeatedly threatened the roadway. City Council awarded the construction bid on February 24, 2025.

Timeline

Each card is one meeting where this item was discussed, oldest first.

Sep 16, 2024 City Council Regular Meeting
Open meeting →
Feb 24, 2025 City Council Regular Meeting Final action here
Action: Award Bid
Carried 7-0
On February 6 and 7, 2020, a large rainfall event occurred in the region, mobilizing a small landslide on King County Parks property adjacent to Newport Way NW. The slide spilled onto the roadway and resulted in the shutdown of a section of Newport Way NW for approximately one week. City, County, and Puget Sound Energy (PSE) crews responded to temporarily stabilize the slide for the short-term.