The 2nd and Bush Intersection Improvements project (Olde Town Traffic Calming, TR 039, Phase 1) was accepted in March 2024 after construction contract award and change orders. The project was completed by Active Construction Inc. at a final contract value of $681,078.70.

Timeline

Each card is one meeting where this item was discussed, oldest first.

Jul 6, 2020 City Council Regular Meeting Final action here
Open meeting →
Mar 18, 2024 City Council Regular Meeting Final action here
Action: Accept Project
Carried 7-0
On April 25, 2022, the City Council awarded the construction contract to Active Construction Inc. for the 2nd and Bush Intersection Improvements (Olde Town Traffic Calming) Project TR 039, in the amount of $646,646. The work included a base bid plus three additional bid schedules. Change Order 1 to this contract was authorized by the City Council on Feb. 6, 2023 bringing the contract total to $681